Category: - Client: Park House Farm, Shawbury - Skill: Renewable - Date: Currently in Construction

Park House Farm, Shawbury, Shrewsbury

Anaerobic Digestion Plant

Date completed – Currently in Construction

 

The Installation

  • Supply and installation of Scottish Power approved switchgear with full interface protection for generation

  • Installation of brick built substation to house the above inclusive of metering

  • Supply and installation of standard Type “A” earthing arrangement

  • Lay  1 x 3c HV cable between Pole 6 & Pole 8, and loop new substation in using 3x 1c HV cable
    to Scottish Power specification

  • Supply and installation of emergency tripping between substation and generation equipment

  • Supply and installation of private transformer complete with bespoke LV cabinet

  • First ICP to undertake a pilot of this configuration of generation connection in the Scottish Power
    Distribution Network area